Saturday, November 10, 2018

everyone knows it's windy!

HI folks,
today, George, Bernard, Ronnie and I helped Fred  to install the angle braces under the bathroom floor which allowed us to fit up the  toilet  flange. The flange plate sits on top of these anglse which Fred welded to the perimeter frame and center sill of the Ping Pong Coach.
It never ceases to amaze me about Fred's expertise. He makes it look so easy.
I even had Bernard take a couple of photos of me testing the toilet to make sure it would hold weight!
And yes, I have no shame!
Enjoy the pictures below.
Gary



Monday, November 5, 2018

do we need service?

we did, but know we don't!
As of this past Saturday, we have PROPER 120 and 240 volt service right where we are working.

So, we took advantage of this and Fred, George, Paul and I installed the first new piece into the Ping Pong Coach.  To us it was HUGE!
To most people, they would look at a 3ft by 9 inch sheet of metal and go, hmmmm.
this part was fabricated by Fred and welded into the south west corner under the bathroom floor and will allow us to add the steel angles that were previously fabricated under what will be an installed toilet flange.
Next week! those angle braces.
Gary

Tuesday, September 25, 2018

In the trenches

Literally!
when you last read about our work, You were able to see a couple of photos of the torn up yard. As of today, Tuesday 9/25/18, except for a very small area by the Ping Pong coach/Tender-the yard looks like it did before all of the digging.
All that is left to do is to run the conductors through the conduit and hook up the circuit breakers and outlets. We will have to fabricate 2 different sized 240 volt/50 amp extension cords to allow us to move the welder inside or under the far side of the Ping Pong Coach/Tender to allow us to weld.
I missed the Volunteer session this past Saturday for a personal issue but can't wait to see what the yard looks like now. In my absence, Steve and Leon had the crew complete many small tasks to update the grounds and for safety sake.
Keep  the faith folks!
Gary

Monday, September 17, 2018

It's Electric-Boogie Woogie

 The photo above shows the newly installed 1 inch line that we have installed for future power to the front gate area.
 The photo above shows where the 3 new conduits are diverging.The biggest one that just stops is a 2+1/2 inch conduit that will provide for 100 amp service to the north east corner where the proposed engine house will be placed

This photo above shows the termination point for the 1 inch line and the 1+1/2 inch conduit that will feed the new 120/240 outlets near the tender and ping pong coach.

Finally, this shot above shows the newly installed 1+1/2 inch line to power the welder and power tools needed to complete the tender and ping pong coach restorations.

George and I will meet our electrician Wednesday morning to install the rest of the 2+1/2 inch line and complete the "rack" for the 120/240 volt outlet installations at the "station" building corner that you see above.

Friday, September 14, 2018

wow, it's been a while

Hi Folks,
It's been about 4 months since I last wrote on my blog, so let me bring you up to date.
Our contractor has been working diligently to complete the west wall of the Historic Presidential Railroad Station and just last week, using the reclaimed lumber we procured, added all new/old window frames to the exterior.
After all of the window frames were completed, They added all six windows. The top 3 are smaller and actually have the interior hardware that allows them to be  opened up for air-flow. The bottom 3 have been sealed up since about 1942!
So, in effect, as it stands today, this side of the station looks exactly like it did back in 1942. Over the last  75 years, these bottom 3 windows have not been seen by the public from the exterior. It sure lets a lot of light into the station.

When that work was completed, they tackled the creation and addition of the missing Tudor trim that was attached over the stucco in many of the panels above the brick.

First shot-before re-installation of  recreated door and windows
Second photo after the new door and windows are installed
Third photo shows the brick after priming
Fourth photo shows the brick after painting. And YES! this is how the brick looked when the station opened up in 1902.
Bottom photo shows the Tudor trim re-installed as well as all 6 windows.
You can easily see that the stucco with the shells embedded in it has NOT been painted over. Again, this is how it was done in 1902.

Yes, that's my shadow.














And Just so everyone knows, we now have Electricity on site.
We had our inspections and PSE&G came in and hooked us up to the grid.
I have posted those photos on our OBRM Facebook page.

Question for all of you--
I am thinking of not writing this blog anymore due to the fact that I am now on Facebook (a decision that was made for me, not by me) and both Steve and I are administrators.
I would think that if you are reading this, you may also be reading our Facebook page.
Please leave me a comment whether you would like me to continue this blog or are you reading this info on our Facebook page.
I'm sure that I can always have our "OBRM BLOG" be changed to a direct link to "OBRM FACEBOOK" Page.
Thank you
Gary

Thursday, May 10, 2018

Late yet once again

HI folks,
sorry I haven't posted in a few weeks, however, I am busy with work and Museum (2 of them) work that has taken up almost all of my "FREE" time.

Simply put,
We have finished up the volunteer portion of the Ping Pong restoration and will have the sandblaster come in, in a couple of weeks to blast the car and the tender.
Until then, we can't work. After that is done, we will let the cars rust over and use Loctite Extend to paint over the rust to form a barrier upon which we can then paint on a coat of primer and finally, after all of the steel work is completed---PAINT!

As for #398, John has been replacing rotted steel that was was hastily installed in order for the LIRR to present them to us. No issues, just time.

We will begin pulling the cables/wiring for the turntable the first week of June and hopefully without any major snags, should be done by the end of the month with the wire installation. Then the fun stuff begins.
We are hoping to have things wrapped up in time for the Oyster Festival!

In a week or so, our contractor for rigging, Pedowitz trucking should have been able to finish the movement in the yard to facilitate the arrival and installation of the 2 LIRR simulators. and make room for the future arrival of our 40 ft ex-New Haven RR boxcar.In the meantime, our station restoration contractor, Mario Baldino has finished up repointing the brick wall on the West side of the station and we had the oyster shells examined to see if they were originally painted or if just the LIRR decided to paint them over many years later. Stay tuned for THAT story.

stay the course!
Gary


Sunday, April 8, 2018

What about us?

Since the weather called for a shitty day, many hands remained at home.
I don;t blame them. Heck, If I could have, I would have too!
I'd like nothing more than to stay in bed all day.
Oh well.
BUT!!!
3 folks did make it up to the bay.
George worked in the ping to get it ready for a Pre-Wash to be performed by our local Atlantic Steamer volunteer Fire fighters.
OK, I can hear you. Dog!? what the hell are you talking about?? A pre-wash? Really??
YES, REALLY!
Look at it from my point of view. IF, the sandblaster, who is using a water based blasting media, has to cut through all of the dirt and dust and whatever, it takes more time. AND, more time=more money that we have to spend.
This Pre-Wash (free, btw) will get rid of the crud and most of the excess grease, leaving less to be blasted off by our contractor.

While George was working in the Ping, Bernard and I were busy restoring windows inside the Historic Train Station building.
Yes, I know its sideways. Use your imagination or turn your screen.
Bernard has just laid out the window and caulked the edges before adding the weatherstripping.

Here is where we began, by taking apart the window frame to ready it for paint stripping and removal of the the weather stripping and operation mechanisms, which are the latches that are on the bottom of the frames. Your left side of the photo.

Here is what the exterior of the windows looked like before stripping.
The 2 vertical pieces are wrapped in a felt material that gets stripped off as well and the piece then gets polished as it seems to be stainless steel.

This is the weather stripping that went around these 2 windows which had come apart. Thankfully, these two are made of safety glass and are lighter than most of the other windows which are not made of safety glass.

At the end of the day, even spending almost 1+1/2 hours each on the 2 broken frames, we still managed to repair 5 windows. My goal is to finish up at least 6 windows per operating session. That would be awesome.

Here is the actual operating mechanism, broken down.
On the right is the piece which you would squeeze to get the window open or closed.
On the bottom is the actuating spring and the shiny bar like piece is a brass casting that is the actuating  or throw rod. This piece, as you can see, is not straight and will need to be heated and straightened out before re-assembly.

Keeping it real since 1962!
I am, yours truly--
Gary T Farkash